Summer 1998 Newsletter 
San Mateo Bridge

 The San Mateo-Hayward Bridge (SMHB) featuring the first major orthotropic steel spans in the United States was opened to Bay Area traffic in 1967. This unique bridge links the peninsula cities of Foster City and San Mateo on the west and Hayward on the east shores on San Francisco Bay. The 7.1-mile long, 4-lane structure carries in excess of 77,000 vehicles in each direction each day as part of the "normal" bay area commuter gridlock. The bridge is comprised of a 5 mile long low level trestle traversing the shallow mud flats on the Hayward (east) side of the bay and a 1.9 mile high level section crossing the navigation channel and finally dropping into Foster City on the west side of the bay.
 As with all of the Bay area Bridges that serve as life lines to the San Francisco Peninsula, the San Mateo-Hayward Bridge needed strengthening to withstand a maximum credible earthquake with minimal risk of collapse.
 The retrofit program on the SMHB is divided into three phases:
 Phase 1 - West Approach & Pier 1 & Pier 1A (Awarded to Dillingham Construction $2,400,000)
 Phase 2 - High rise portion (Awarded to Morrison Knudsen / Traylor Bros. / Weeks JV $102,000,000)
 Phase 3 - Seat extenders, Miscellaneous Piling and Seismic Instruments, (Trestle section) (Awarded to West Coast Bridge $7,500,000)
 On November 4, 1997, Traylor Pacific, in joint venture with Morrison Knudsen, of Boise, Idaho,  and Weeks Marine, of Cranford, New Jersey, (MK/T/W)  was low bidder on the largest and most complex contract of this retrofit program.
 Work began in mid-March on the project after a long mobilization of a marine fleet by the JV Partners. Before the year is out, this team will have developed schemes and techniques to strengthen this structure in ways uncommon even in the retrofit market. These techniques include:
á Expansion & Tied Hinges for Main Structure: New vertical hanger rod assemblies will be installed except at the expansion and tied joints of the channel span, which will have vertical hairpin shaped assemblies. New longitudinal rod restrainer systems will also be installed at all expansion and tied joints. The shear lock assemblies in the box girders will be removed and replaced with larger assemblies.
á Expansion Joints at Piers 1 & 38: The expansion joint capacities will be increased to two feet by using 2" thick steel cover plates.
á Bearings at Piers 2-37: New vertical restrainer bar assemblies will be installed.  Existing bearing pins will be strengthened with new steel pipe key assemblies except at Piers 19 & 20. The bearing plate assemblies at Piers 19 & 20 will be strengthened with new reinforcement.
á Steel Towers at Piers 12-27: Steel plates will be installed on the vertical faces of the towers, and stiffener members will be installed in the spandrel beams. Over 250,000 stitch bolts will attach the new plates to the tower faces. Additional vertical anchor rod assemblies will be installed at the base of the towers, and six-feet of reinforced concrete will be placed inside the base of the steel towers.
á Concrete Spandrel Beams at Piers 2-18 & 21-37: The spandrel beams and joints at Piers 2-11 & 28-37 will be jacketed with post-tensioned concrete cover. The lower hollow spandrel beams at Piers 12-18 & 21-29 will be filled with grout and post tensioned vertically.
á Rectangular Foundations at Piers 2-13 & 30-37: A cofferdam will be installed to access and place a concrete overlay on top of the pile cap. Four open-ended large diameter (12’0" dia. X 2 ¹" thick) steel shell piles, weighing up to 275 tons will be driven at the corners of each pile cap. The top 15’ of the piles will be filled with concrete. A new precast concrete "dog-bone" collar will encase the newly thickened pile cap footing. Each precast frame weighing in excess of 500 tons will be fabricated in two halves, floated into position around the pier, connected and stressed, then lowered down onto the large diameter steel shell piles.
á Bell Foundations at Piers 14-18 & 21-29: Excavation to the bottom of each pile cap will be required for the placement of the steel jackets to encase the cylindrical portions of the bell foundation. After the steel jackets are installed, grout will be injected to fill the void between the existing concrete and steel jacket.
 Currently dredging operations have begun on Pier 31, 30, 21 & 12. Concrete spandrel work has begun on piers 31 & 30. Structural steel has begun with the opening of access holes at the 38 hinge areas on the superstructure. Current project completion is scheduled for December 1999.
 

NEXT ARTICLE

Sailboat Bridge

Greetings from the cowboys over yonder in Grove, Oklahoma! Work is well under way at the ranch in this lake resort town. Despite the constant 90 plus degree weather, Traylor Bros. is getting some hard work out of the crews in the casting yard. Having cast 57 of the 356 superstructure segments for the Sailboat Bridge, everyone is finally starting to see some tangible results for all those long hours on the clock. The drilled shaft crew over at the bridge site is also working hard, as they have poured the drilled shafts for abutment 26 and pier 24. Back at the casting yard, construction of the precast tubs for the footings has just begun, as the first of 48 footings is being formed. When the drilled shaft construction gets into full swing, the bridge site will become very busy. The placement of the footings, columns, and caps for the northbound lane will soon follow, and the citizens of Grove will see their tax dollars being put to good use. Erection of the northbound superstructure is slated to begin this winter, and the transfer of traffic to the new bridge is set for late May of 1999.
 New workers are being hired every day to accommodate the footing construction and to increase production of the precast segments. Even more help will be needed when we start working a night shift. The plan is to set and strip during the day and pour at night to beat the heat; we are not allowed to pour when the ambient temperature exceeds 95 degrees, which will happen too often this summer.

NEXT ARTICLE


 

Vincent Thomas Bridge

Only a handful of readers will ever have the opportunity to seismically retrofit a bridge in Southern California. Even fewer  will have the opportunity to retrofit a suspension bridge in the area. Traylor Pacific has both.
 Over the next few issues of the Traylor newsletter, we will explain some of the unique elements of the Vincent Thomas Bridge project. The first article explains the installation of the truss fuse.
 The truss fuse system utilizes viscous dampers coupled with hinged connections to provide a movable section of the bridge. The purpose of the truss fuse is to dissipate energy transmitted to the bridge by an earthquake. The truss fuse consists of:
 *  Pin Plate Assemblies - These assemblies provide a pinned connection at the top chord of the stiffening truss. This connection acts as a hinge, or pivot point, for movement generated by a seismic event.
 *  Viscous Dampers - The viscous dampers connect the severed bottom chord of the stiffening truss. These dampers are similar to hydraulic shock absorbers on a car. They transform kinetic energy (movement of the bridge created by an earthquake) into heat. This helps avoid structural damage to the bridge members. The silicon impregnated viscous dampers have a range of motion of 16" and can withstand axial loads of 265 kips.
 *  Link Plates - The link plates connect the severed bottom chord of the suspended truss. These plates are designed to break at a pre-determined point. Once enough force is generated to break the plates, the forces on this chord are transferred to the viscous dampers.
 *  Shear Tongue - The shear tongue assembly allows the bridge to move axially while prohibiting lateral movement. If a seismic event created enough force to break the link plates and transfer the load to the dampers, the shear tongue would provide the needed lateral support.
 Work is done on the weekends, while the bridge is shut off to traffic, so that no unnecessary loads are imposed. Crews work around the clock to complete the following work before the bridge is to open again Monday morning:
 *  The shear tongue assembly is installed in the floor truss system.
 *  Ironworkers torch-cut the top and bottom chords of the suspended truss in order to install the hinged connections and the dampers. Temporary supports are installed to hold the truss together while the cuts are made.
 *  Hinge plates are installed on each end of the severed top chord. An 8" pin is driven through holes in the plates to form a hinged connection.
 *  Link plates are installed connecting the severed bottom chord of the suspended truss.
         *  The viscous dampers are installed in the bottom chord of the truss.
 Thanks to the hard work of the Traylor Pacific staff and crew, four truss fuses were installed in the month of June - one each weekend.
 

NEXT ARTICLE

Roger Foreman Promoted

 Roger Foreman has been promoted to President of Traylor Bros. The decision was announced at the annual meeting of the Board of Directors in April.
 Tom Traylor, former president, retains the titles of Chairman of the Board and Chief Executive Officer.
 Congratulations, Roger!
 
 

 
 

NEXT ARTICLE

Test Your Safety Knowledge

 Let's test your safety knowledge! See how many of the five questions you can answer without looking at any reference material. The correct answers, in accordance with federal OSHA Construction Industry Standard, are provided _______________.

 1. How many pounds of force must an anchor point be able to withstand?

 (a) 500 (b) 50,000
 (c) 5,000 (d) 50

 2. OSHA 1926.501 requires employers to provide fall protection when employees are exposed to a fall of ____ feet or more.

 (a) 5 (b) 10
 (c) 6 (d) 25

 3. OSHA uses the 5(a)1 General Duty clause to cite employers for all health and safety violations?

 (a) True (b) False

 4. As defined by OSHA in Subpart M, a HOLE means "a gap or void ____ inches or more in its least dimension, ..."

 (a) 2 (b) 10
 (c) 12 (d) 4

 5. According to OSHA, the top rail in a guardrail system must be capable of withstanding a force of ____ lbs in any direction.

 (a) 200 (b) 5,000
 (c) 2,000 (d) 50,000

 How did you do? If you answered any of the questions incorrectly, you may want to check with your foreman for more information concerning these topics. Remember, information is knowledge, and well-informed employees are able to work smarter and safer.
 Our goal, as always, is to "Build America Safely."
 Answers to Safety Quiz:

(1) c
(2) c
(3) False
(4) a
(5) a
 
 

 
 Return to Traylor Home Page