Fall 1997 Newsletter 
Vincent Thomas Bridge Seismic Retrofit

"Tuesday morning, Joe’s laborers are scheduled to sand blast the south, upper column area, Bent 5. Pete’s carpenters will finish the dowel template work at north upper column, Bent 5 and move to the south leg by noon. The falsework erection
crew is scheduled at both legs of Bent 5 Wednesday a.m. Rod busters get Thursday (no matter how many hours it takes) and the pour is positively confirmed for noon on Friday." This conversation (or something very similar) is heard 3 or 4 times each
day in Traylor Pacific field office on the Vincent Thomas Bridge. Let us mention that the name of the game in the seismic retrofit market is schedule, not monthly schedule, nor weekly, nor daily, but hourly schedule. Superintendents and project support staff are continually coordinating the minute movements of 30-40 craftsmen spread over at least a dozen work areas in a mad scramble to upgrade these structures prior to the next "big one." It is not that the retrofit work is that difficult (or even complicated) but rather that the quantities of work are spread over such large areas of the job. For example, over the next 14 months the team at the Vincent Thomas Bridge will place 6,400 cubic yards of structural and footing concrete. Now 6,400 CY is a respectable quantity and one that would usually generate some level of economies of scale on a typical heavy civil job. What you don’t see though is that the design dictates this quantity be broken-up into over 210 pours (for an average pour of 30 cubic yards). At this level of dispersion (or disruption) the schedule looks more like that of a residential homebuilder than that of a heavy construction contractor. Each work activity on the job bears these similar traits: decent quantities spread over huge work areas. So the name of the game has to become schedule: the art and science of moving crews and equipment efficiently
between work locations. The State of California has been seismically upgrading its 2,400 + bridge structures since the February 1971 Sylmar earthquake which resulted in the collapse of several major structures in the San Fernando Valley. The Northridge earthquake (6.8 on the Richter scale) in January of 1994 accelerated the statewide retrofit program and brought validation to several key design assumptions of the retrofit strategy. On each retrofit, be they a $500,000 overpass project or $100,000,000 Bay area bridge, we usually see similar design philosophies: Foundation Improvements: Typical foundation retrofit involves installation of additional support piling to either increase the bearing or uplift capacity of the footing or provide greater lateral capacity. Footings are usually thickened or enlarged to increase the reverse moment capacity at the column/footing interface.
Column Improvements: Column retrofit usually involves installation of a jacketing system to confine the concrete around the vertical reinforcing steel. Jackets are made of a thin steel plate, reinforced concrete or spun carbon filament. Cap Improvements: Pier caps are typically thickened to improve their ability to handle large lateral loads and/or to force plastic hinging into specific areas. Concrete blocks are usually added to the top of the caps to confine (or trap) the superstructure
members on top of the pier. Bearing Retrofits: The 1994 Northridge earthquake surprised the entire community with not only the magnitude (or intensity) of the event but also with the level of horizontal movement experienced by even the newest
structures. Typical bearing improvements now involve the removal and replacement of existing rocker/fixed bearing assemblies with elastomeric or PTFE bearings that tolerate significantly larger ranges of motion. Super Structure Improvements: In a
final effort to control the larger movements of the structure, several areas are usually modified: á Expansion joints are modified (increased) to allow the structure greater longitudinal movement. á Simple supported girders are tied together across pier tops
to prevent single units from falling off the supporting surface. á Hinge joints are restrained to prevent excessive movements. á And finally, shock-absorbing devices known as "viscous dampers" are installed in some structures to dissipate some of the
seismic energy as it moves through the structure. Traylor Pacific’s $25,000,000 project on the Vincent Thomas Bridge involves many of these improvements. Over the next 14 months crews will install: á 1,500 cubic yards of structural concrete to
thicken the existing column footings. á 4,900 cubic yards of structural concrete to jacket the existing columns and thicken the pier caps. á 72,000 lineal feet of rock drilling and bonding of rebar dowels into the existing pier faces. á 14,000 lineal feet
of core drilling concrete core drilling for the grouting of high strength rods. á Jacking and removal of 44 of the existing bearings supporting the approach span plate girders and installing PTFE sliding bearing replacements. á Installation of threaded
rod systems between each of the girder ends on top of each pier. á Strengthen the floor truss and bottom laterals on the suspension spans. á Modify the existing expansion joints at the cable bents. á Strengthen the existing towers. á Install 48
viscous dampers in the truss side span, truss/tower and cable bent areas. á Install maintenance traveler and rail system on the 1800-ft west approach. á Removal and replacement of 14 of the existing suspender cables. As of early September, the
footing and column work is well under way on the west approach of the structure. The steel erection work is just beginning with the installation of access scaffolding near the east tower of the suspended span. The entire project is scheduled to be
complete in early October 1998. Traylor Pacific is delighted to be involved in the first toll bridge retrofit contract in this the final phase of CalTran’s bridge upgrading effort. The project not only provides the division with a valuable "1st job" but also
provides enviable insight to our estimating efforts on similar bridgework in the bay area. (More about the detailed progress of Joe’s laborers in future editions.)

NEXT ARTICLE

17th Street Causeway - Ft. Lauderdale, FL

Traylor Bros. executed a contract with the Florida Department of Transportation on 07/31/97 to construct a mid-level bascule bridge over the Intracoastal Waterway on the 17th Street Causeway in Fort Lauderdale, Florida. This bridge will be 1,908 feet long with dual 53.5 foot wide roadways, and provide a 125 ft wide by 55 ft vertical clearance at the waterway when closed. Vertical clearance, when the span opens, will be unlimited. The bridge consists of nine approach spans of precast segmental superstructure on C.I.P. piers and drilled shaft foundations, and a twin-leaf bascule span of 242 ft. The structural steel bascule spans rest on Y-legged "carina" piers of post-tensioned, C.I.P. concrete, on drilled shaft/cofferdam foundations. Work is slated to begin the first week of November 1997. The first (north) half of the new bridge is scheduled for completion by January of 1999. The total project, including the south bridge and all roadway and approach work, is to be completed by April of 2000, a total of 900 contract days. To begin the project, Traylor must complete the landside spans of a temporary bascule bridge already under construction. Remaining to be completed by Traylor is 24,450 sf of bridge, consisting of 15 thirty-foot spans of precast concrete slab deck, and three spans, totalling 240 ft of precast deck panels on structural steel. The substructure will be constructed utilizing 18 precast bent caps and over 8,100 lf of 20" steel pipe pile. Also required is 25,000 sf of temporary sheet pile walls, with 39 tie-backs, to contain the temporary embankment. Once two lanes of traffic are placed on the temporary bridge, demolition of the north half of the existing bridge can commence. The existing concrete on steel girder approach spans will be split down the middle, with the north two lanes being removed. The existing bascule span must remain
intact, because the steel and machinery arrangement will not allow it to be cut in two and still function. Temporary falsework protection must be installed over the existing bascule counterweights to ensure that no damage occurs during construction of the
new carina piers above them. Also included in this phase is an additional 24,300 sf of temporary sheet piling and 44  prerestressed anchors, to allow for the excavation of the existing embankment. There are a total of 113 each of 42" drilled shafts required for the new bridge, plus four test holes/demonstration shafts, totalling 8,823 lf of shaft. Also required are four Osterburg cell load tests, and one lateral load test. Prior to beginning drilled shaft work, each shaft location requires a core sample. There are over 5,660,000 lbs of rebar in the job, just over 19,500 lf of steel and aluminum railings required, 86,650 cy of embankments and surcharges, as well as 37,533 sf of temporary and permanent Tensar MSE wall systems. The stainless
steel-clad control house has 470 sf of tinted, bullet proof glass. Total existing bridge area to be demolished is just over 60,000 sf and requires that the existing bascule pier, including piling and seals, be completely removed. Cofferdams are required to
limit environmental degradation during demolition of these piers.
 

NEXT ARTICLE


Fulton Street Bridge Pump Station

In May of 1997, Fulton Street Bridge crews changed hats to begin installation of a
water collection system and the reconstruction of a pump station. The project was
let in two contracts. One for $98,000 to supply the pumps which had a four month
lead time and another for $840,000 to do the job. The Fulton Street Underpass has
been known to frequently swallow cars during heavy rains (not 100 year rainstorms,
but 1/2 year rain storms for you municipal storm water planning types). The first part
of the project consisted of the collection system. Seventeen catch basins and 1,000
ft of pipe, ranging from 18" diameter to 36" arch pipe replaced two catch basins and
100 ft of 15" pipe along Fulton and Overton Streets. Crews followed with 1200 ft
of base and concrete patchwork. The challenge for this phase was working in and
out of traffic which was narrowed down to two lanes from four lanes with no
shoulder access. It also convinced the former Superintendent that he’d rather be
driving a dump truck, which, by the way, is his new occupation. The second piece
of the project consisted of replacing two 12" discharge pumps and motors with four
new 60HP 1200 RPM motors which powered four 16" discharge, 12.5 cfs pumps.
The key challenge on this phase of work has been converting the existing dry/wet
well system into a complete wet well system. Several pairs of waders were worn
out during this work. By the end of the project, we learned the measure twice, cut
once theory. All in all, the pump station adventure has been a success with the
exception of one recordable injury. The rest of the job is 99% complete with minor
punchlist items to complete. A thank you and dedication luncheon was held on
Friday, August 22, 1997, to recognize all who have helped bring the Fulton Street
Bridge and Pump Station to completion.

Text 3

NEXT ARTICLE

Sailboat Bridge Project

The Heavy Civil Division recently signed a contract for the Sailboat Bridge project,
near Grove, Oklahoma, which bid August 21. The twin 928m (3,044') long bridge
will replace the existing two lane bridge built in 1937 to carry U.S. 59 over Grand
lake. One of the bridges will utilize 16 of the original bridge piers to reduce
foundation costs in the 21m (70') deep water. Spans are 37m (122') to match the
existing bridge pier spacing. Vertical navigational clearance will be 15.8 m (52'),
which will open the northern end of the lake to boats in the area. Complex phasing
will be required to maintain traffic during construction.
 
 

NEXT ARTICLE 



 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

HCD Low Bidder

On Friday, September 26, Traylor Bros. Heavy Civil Division was apparent low bidder on a
new 4,510' cable stayed, twin tower, bridge project. The bridge spans the Ohio
River and Indiana 66 near Rockport, Indiana, and Owensboro, Kentucky (US
231). The Kentucky Transportation Cabinet will oversee the project expected to
start-up in early December 1997.
 
 
 
 

NEXT ARTICLE

Patton Island Bridge Superstructure
        A note from Evansville about this project:  as the photo at left illustrates, this project was built in the tailwaters of the Tennesee River dam at Florance, AL.  River currents were as high as 8 mph, and the bottom was slick bare rock.  You can imagine the challenge working in these conditions!  Also note our 4100 Manitowoc ringer and barge that was utilized to set these unusually heavy girders.
        August was a good month for Traylor Bros. at the Patton Island Bridge project. Completing several work items and a relatively dry month has helped promote a more rigorous schedule, making up for numerous lost inclement weather days and bringing the
project to 75+ percent completion. Accomplishments to date: -Completed setting bulb tee girders (247 total) -Diaphragms completed 716 of 884 or 81% -North bound bridge deck concrete - "completed" all 13 spans (Pumped final span
concrete 1920 lf for a total of 3000 cy placed in the north bound deck -South bound bridge deck concrete - 1st of 13 spans placed -Stay in place decking - working in Span 11 south bound bridge (62%) -Barrier wall concrete - 6 east side
spans of the north bound bridge -OSHA jobsite visit - no citations recorded We are pleased and proud that everyone is participating in the Safety Awareness Program.  Providing and maintaining a safe workplace is everyone’s responsibility. Good luck for continued success!
 

NEXT ARTICLE

On-the-Job Training Program, Neuse River Bridge

The Federal Aid Highway Act of 1968 was passed by the 91st Congress. It
included a special section devoted to promoting and insuring equal employment
opportunity in the field of Federal-Aid highway construction. The Act outlined how
the incorporation of equal opportunity legislation and regulations would be
accomplished and reiterated that inclusion of these provisions reflected the
congressional commitment to the development of an effective equal employment
opportunity program because "they believe in the essential correctness of such a
program." All OJT programs approved for use embody the objectives of fairness
and equity as required by the Code of Federal Regulations 23 CFR Ch. 1, Sub Part
C, Section 230,.307 which reads: "Every employee and representative of State
Highway Agencies shall perform all official equal employment opportunity actions in
an affirmative manner, and in accord with the applicable statutes, executive orders,
regulations, and policies enunciated there under, to assure the equality of
employment opportunity, without regard to race, color, religion, sex, or national
origin both in its own workforce and in the workforces of contractors,
sub-contractors, and material suppliers engaged in the performance of federal-aid
highway construction contracts." Upon setting up the project site in New Bern,
North Carolina, on the Neuse River, Traylor Bros. made a commitment to
implement the North Carolina DOT On-The-Job Training Program. The primary
objective of the NCDOT OJT program is to provide training opportunities for
women and minorities which will increase their participation in every craft
classification in the highway construction industry. There are two types of training
that are generally recognized, apprenticeship and self-administered on-the-job
training programs. Apprenticeship programs usually require at least some classroom
instruction time and are one to four years in duration. In North Carolina, however,
most training is done through approved On-The Job Training Programs. Training
and supervision is provided by the contractor for an employee who is enrolled in an
approved training program for a given classification and position. Employee
compensation during training is governed by the Davis/Bacon Act and the project
special provisions of the contract. Contractors responsibilities include having an
Affirmative Action Plan and Policy in place prior to beginning any federal aid
project. Submission of a trainee training schedule is due prior to the preconstruction
conference set for a particular project. Contractors decide whether trainees are
selected from their current workforce or whether special recruiting will be
undertaken. OJT trainees are enrolled on approved forms and submitted to the
Resident Engineer for approval. The contractor orients the training foreman,
superintendent, and OJT trainee to their individual responsibilities in the program.
The contractor annotates the certified payroll and is required to show training hours
as distinct from regular hours for each OJT trainee and submits weekly. The
contractor monitors all trainee progress and notifies the Resident Engineer within five
working days of any trainee terminations. Contractors can assign training positions
to subcontractors but still retain the responsibility for full compliance with the OJT
trainee requirements. Since early 1996, Traylor Bros. has had 31 trainees enrolled in the OJT
program. Of that 31, seven have graduated the program, and seven have
terminated. There are currently 17 still enrolled and undergoing on-the-job training.
Of notable mention, Neuse River project’s first OJT trainee graduated the dozer
operator training program in approximately seven months time and is now a foreman
on the jobsite. We salute these employees and wish them much success in
continuing their careers with Traylor Bros..

Text 7

NEXT ARTICLE

Title 8

Text 9

NEXT ARTICLE

Title 9
Text 9

Return to Traylor Home Page