Louisiana Highway LA1 Relocation PDF Print E-mail

mt_noneLouisiana Highway LA1 Relocation (Phase 1B and Phase 1C) ( tbi0601 & tbi0603)
Leeville, Louisiana
Construction of a 4-mile long high-level bridge with connecting ramps and interchanges.

 

 



through 04/2010

Louisiana Highway LA1 Relocation - Phase 1B
Leeville, Louisiana
Construction of a 4-mile long high-level bridge with connecting ramps and interchanges. Work consists of 16", 24", & 30" prestressed concrete pile foundation, cast-in-place substructure, type lll and BT-78 prestressed concrete girder, precast deck panels and cast-in-place concrete deck.



LA1 Over Bayou Lafourche at Leeville, Phase 1C - Main Span
Leeville, Louisiana

Description - 0.165 mile main span structure over Bayou Lafourche. Work consists of 30" prestressed concrete pile foundation, cast-in-place substructure, welded steel plate girder, and cast-in-place concrete deck.

 

   

Project Gallery:


Phase 1B
Construction Method: Precast Concrete Girder
Contract No: 829-32-0007
Start Date:  Notice of Award 01/26/06; Notice to Proceed 03/01/06 
Completion Date: 3/22/2010
Owner:  Lousiana Department of Transportation and Development
Joint Venture:  Traylor/Massman

Phase 1C - Construction Complete
Construction Method: Steel Plate Girder 
Contract No: 829-32-0008
Start Date: Notice of Award 04/05/06; Notice to Proceed 01/29/07
Completion: 2/4/09
Owner: Louisiana Department of Transportation and Development
Joint Venture:  Traylor/Massman