Construction began January 2007 for 1.1 miles of new, twin bridges composed of driven 36" square piles, bent caps, waterline footings, columns and pier caps, BT-78 precast concrete girders, structural steel mainspans & poured in place deck.
Through March 2010:
Piling: All bent and pier pile have been driven (1056).
Footings: All 32 footings have been poured.
Crashwalls: All 32 crashwalls have been poured.
Columns: All 64 columns have been poured.
Pier Caps: All 32 pier caps have been poured.
Bent Caps: All 50 bent caps have been poured.
BT-78 Beams: All 76 spans have been set in place.
Structural Steel: All westbound and eastbound spans have been set.
Decks: All 81 deck spans have been poured.
Project Gallery:
Construction Method: Precast Concrete Girder
Contract: 450-17-0028 Start Date: Notice of Award 12/06/06
Notice to Proceed 01/25/07 Completion Date: In Progress Owner: State of Louisiana Department
of Transportation and Development
Joint Venture: Traylor/Kiewit/Massman