Safe and Sound Bridge Improvement Design-Build – 554 Bridges, Statewide, MO
The Missouri Dept. of Transportation’s (MoDOT) Safe and Sound Bridge Improvement Program.
| The largest bridge improvement project in Missouri history, will repair or replace 802 of Missouri’s most structurally challenged bridges over four years.Approximately 1,100 bridges are either Condition 3 (serious) or Condition 4 (poor). A key component of the Safe and Sound program is the $487-million design-build effort to replace 554 bridges in 111counties. Key Facts Market: Transportation Service: Bridge Structures Project Value: $490 million Start Date: 2009 Completion Date: 2013 As of early October 2011, the team has completed 363 of the 554 bridges, with 47 currently under construction, averaging 45 days per bridge, and each with an outstanding record of safety, quality and stakeholder satisfaction.
|